Latest news
Photo 260626

Norris Watson Drive - June Update

1 min read
June 30, 2026

As we head into the middle of the year, building inside and out, still progresses.

The team are now beginning to enclose the ELA, steel work for the frozen holding room is going up, and the truck docks are starting to take shape.

Around the back the refrigeration team are busy installing plant and low oxygen fire prevention systems.

Inside, the racking team are beaving away errecting the 15,000 pallet spaces of ASRS racks.