Latest news
Norris Watson Drive - March Update
As we roll into March, the progress on our development forges ahead.
Concrete foundations are complete, the steel work for the main store is being erected, and insulated panels are beginning to go up.
Towards the back, the concrete tilt slab for the plant room is rising, and out front, the office wall framing and roof are in place.
The next few weeks will see similar progress, but it is all shaping up to be an impressive facility.