Norris Watson Drive Build

1 min read
January 15, 2026

Towards the end of last year, in the very early hours of the morning, we began a marathon concrete pour for the base slab of our Norris Watson Drive cold store project.

With a volume of approx 1,000 cubic metres, this was significant, and took nine hours to complete.

We now move onto the steel stage, and the framing for the offices.